EMH Group misses development target by 40%

accounts balance sheet

Housing association says build hit by planning delays, materials shortages and pandemic impacts but is confident of hitting five-year target

EMH Group built 60% of its targeted homes in 2021/22 as it battled planning delays and materials shortages, its latest accounts show.

The east Midlands-based housing association completed 343 homes in the year but was originally aiming for 550.

It said: “This shortfall is largely due to the ongoing impacts of the pandemic and Ukrainian crisis as materials and resource become harder to secure coupled with delays on planning being awarded therefore delaying start on site.”

Login or Register for free to continue reading Housing Today

To continue enjoying housingtoday.co.uk, REGISTER FOR FREE

Already registered? Login here

Stay at the forefront of thought leadership with news and analysis from award-winning journalists. Sign up below to receive:

  • Breaking industry news as it happens
  • Gain access to Housing Today’s Specialist CPD modules
  • Expert News and analysis

It takes less than one minute….

Join the Housing Today community - REGISTER TODAY

… or subscribe for full access - Subscribe now