Developer insists arrangements already in place as housing secretary orders officials to review buildings developer has assessed as safe
The housing secretary has written to developer Galliard expressing “significant concern” about its conduct since the evacuation of several buildings in east London.
A total of five towers in the Caxton Works/Royal Gateway scheme, completed by Galliard in 2018, have been evacuated over several weeks in October, with Newham Council serving Dangerous Structural Notices for three of the buildings.

On Tuesday, Angela Rayner wrote to Stephen Conway, non-executive chairman at Galliard, telling the developer to “honour your promises without delay”.
She noted that the “situation did not come about suddenly”, noting that Galliard was first asked about the construction on 13 May and that the decant of the first buildings was ordered on 22 October.
“My officers suggested you needed help with temporary accommodation on 4 November, but you did not appoint anyone until 17 November, nearly two weeks later,” she claimed.
Galliard announced its commitment to “reimburse reasonable relocation and temporary accommodation costs” on 5 November and on 17 November it confirmed its appointment of ICAB, a specialist temporary accommodation provider, to find and book suitable nearby temporary accommodation.
The developer promised to pay the cost directly and to provide accommodation for up to three months from 12 November, or until residents can return to homes safely.
Rayner said the delay in appointing a specialist had “left residents to foot the bill for temporary accommodation” and that “some have such little faith in your promise of reimbursement that they have chosen to remain in or even return to buildings with structural defects that pose an imminent risk to life”.
“I wonder if Galliard would have been so slow to do the right thing if your chief executive still owned a penthouse flat at Caxton Works,” she added.
A spokesperson for Galliard said they had “already put temporary accommodation and reimbursement arrangements in place for Royal Gateway residents” and stressed that they shared Rayner’s “determination that residents receive the support they need, and our focus is on getting that support to them as quickly as possible”.
They said that residents using ICAB’s service “do not have to pay upfront or claim those costs back” and that “each household’s circumstances and accommodation needs are considered individually”.
“We have a dedicated building safety team that works closely with MHCLG, the Building Safety Regulator, freeholders, managing agents and leaseholders to identify solutions and support those affected by any issues related to building safety,” they added.
“This support is provided without admission of liability and without prejudice to Galliard’s position, including any rights against third parties.”
At the end of her letter to Conway, Rayner stressed that “as long as residents are unable to return home, they will have financial and practical needs that I expect Galliard to meet”.
She noted that Galliard was among the last to sign the government’s remediation contract and said that this demonstrated an attitude of “putting finance before fairness”, which she said seemed “sadly still too prevalent in your company today”.
Rayner also said that she had ordered her officials to “begin an urgent review and assurance of Galliard buildings that you have assessed as not requiring works”.
After a meeting with Baroness Blake, a minister in Rayner’s department, Galliard and other parties have agreed to meet daily over the next five days to resolve outstanding practical issues.
Ground investigations and building monitoring are continuing at the site, with engineering investigating structural concerns and developing proposals for required works.