Grenfell project manager didn’t read safety report despite ‘Lakanal moment’

Grenfell Tower toward the end of its ill-fated refurbishment

Source: Grenfell Tower Inquiry

Client’s lead tells inquiry she wanted clarification on west London tower’s cladding following 2009 fire in Southwark

The client side project manager tasked with overseeing the refurbishment of Grenfell Tower has told the inquiry into 2017’s disaster that she flagged concerns spurred by 2009’s Lakanal House fire but did not read a key safety document in relation to her own scheme.

Claire Williams, who was Kensington and Chelsea Tenant Management Organisation’s project manager on the Grenfell refurbishment from 2013 until its practical completion in 2016, said she knew a contractor connected with the earlier Southwark fire and understood cladding was an issue.

Login or Register for free to continue reading Housing Today

To continue enjoying housingtoday.co.uk, REGISTER FOR FREE

Already registered? Login here

Stay at the forefront of thought leadership with news and analysis from award-winning journalists. Sign up below to receive:

  • Breaking industry news as it happens
  • Gain access to Housing Today’s Specialist CPD modules
  • Expert News and analysis

It takes less than one minute….

Join the Housing Today community - REGISTER TODAY

… or subscribe for full access - Subscribe now