NHBC figures show impact of gateway 2 hold-ups on London market
The impact of building safety regulations hammered the number of new homes being built in the capital in the second quarter of this year.
Figures from the National House Building Council (NHBC) show registrations slumped 59% in London to just 904 in the three months to June.
The NHBC, which provides new home warranties and insurance, said: “London saw the biggest fall as the capital continues to be affected by the new building safety regime for high rise buildings and a depressed level of activity from housing associations.”
But this week’s figures show 30,405 new homes were registered to be built in Q2, up 4% the same period last year and 4% more than the first quarter of this year.
Across the UK, six out of 12 regions saw a rise in registrations in Q2 compared to the same period last year, with the highest increases in Yorkshire and Humberside (+96%), the South west (+75%) and Northern Ireland (+44%).
NHBC chief executive Steve Wood said: “While some areas of the market remain subdued, we remain optimistic about the longer-term as planning and land restraints are increasingly unblocked, mortgage rates ease and the Government sustains a focus on new home delivery.”
Recent figures from the Building Safety Regulator show that the average amount of time it is taking to get gateway 2 safety sign-off is nine months – three times the planned 12 weeks timeframe.
More on the gateway 2 delays
Streamlining gateway 2: time for a two-tiered approach to building safety approvals?
Building safety sign-off problems spooking investors, Quintain boss tells Lords
Lords opens inquiry into Building Safety Regulator scheme approval delays
The housing sector needs a Building Safety Regulator that is fit for purpose
Building Safety Regulator considering taking ‘firmer approach’ to bad gateway 2 submissions
What the delays at the Building Safety Regulator mean for high-rise development
Homes England boss calls on government to fix ‘unacceptably slow’ gateway 2 approvals
Government exploring ‘all possible options’ to cut gateway 2 building safety delays, says minister
No comments yet